2016.07.01 - 7.5 Hours - Caulking, Header Install, Floor Cleaning for Flooring Install

2016.06.30 - 7 Hours - Priming Studio and Bathrooms

2016.06.28 - 7.5 Hours

Payment math for 6/27

8+7.5+7+7+7.5+7.5 +7.5+8+9.5+7

76.5×20 = 1,530

1,530+30+63.36

1,623.36 (Owed to date)

- 1300.00 Paid 6/27

323.00 Left for 6/27 Payment

---

2016.06.27 - 7 Hours

2016.06.24 - 9.5 Hours - Painting, Mudding, Water Putty, Caulking

2016.06.23 - 8 Hours

2016.06.17 - 7.5 Hours - Painting, Cleaning

2016.06.14 - 7.5 Hours - Water putty, Window Pickup, cleanup, Mudd mix

2016.06.14 - Receipt 63.36 - Mudd and 2x3:

2016.06.13 - 7.5 Hours - Caulking and Plastering

2016.06.10 - 7 Hours - Caulking

2016.06.07 - 7 Hours - Finished paint prep for master bedroom, cleaning, insulation.

2016.06.03 - 7.5 Hours - Sanding master bedroom, caulking studio, cleaning

2016.05.31 - 8 Hours - studio wall prep for paint, caulking, bathroom wall and sink pickup

2016.05.31 - $30 Truck usage.

2016.05.30 - Paid to date.

2016.05.27 - 8 Hours

2016.05.27 Expenses - 295.93 5 Gal white, 5 Gal grey exterior paint. ($80 in rebates! Be sure to send in!)

Receipt:

2016.05.24 - 8 Hours - Bathroom framing, plumbing help, backing.

2016.05.20 - paid to date.

Total Hrs Not Paid as of 5/17: 27 + $46 Incidentals

2016.05.20 - $14 Truck Usage

2016.05.20 - 5 Hours - Dirt Moving, Floor Pulling (finished!), and cleaning.

2016.05.17 - 7 Hours - Dirt Moving and Leveling / Floor Pulling

2016.05.13 - 8 hours - 2 loads of dirt, sliding door pickup, and general cleaning.

2016.05.13 - $30 for truck gas and usage

2016.05.13 - $16 dump fee

2016.05.10 - 7 hours