Davenport Hours

From Sharemoon.pub ~ Community System Blueprint
Revision as of 17:00, 14 June 2016 by Morishigejoe (talk | contribs)
Jump to navigation Jump to search

2016.06.14 - 7.5 Hours - Water putty, Window Pickup, cleanup, Mudd mix

2016.06.14 - Receipt 63.36 - Mudd and 2x3:

2016.06.13 - 7.5 Hours - Caulking and Plastering

2016.06.10 - 7 Hours - Caulking

2016.06.07 - 7 Hours - Finished paint prep for master bedroom, cleaning, insulation.

2016.06.03 - 7.5 Hours - Sanding master bedroom, caulking studio, cleaning

2016.05.31 - 8 Hours - studio wall prep for paint, caulking, bathroom wall and sink pickup

2016.05.31 - $30 Truck usage.

2016.05.30 - Paid to date.

2016.05.27 - 8 Hours

2016.05.27 Expenses - 295.93 5 Gal white, 5 Gal grey exterior paint. ($80 in rebates! Be sure to send in!)

Receipt:

2016.05.24 - 8 Hours - Bathroom framing, plumbing help, backing.

2016.05.20 - paid to date.

Total Hrs Not Paid as of 5/17: 27 + $46 Incidentals

2016.05.20 - $14 Truck Usage

2016.05.20 - 5 Hours - Dirt Moving, Floor Pulling (finished!), and cleaning.

2016.05.17 - 7 Hours - Dirt Moving and Leveling / Floor Pulling

2016.05.13 - 8 hours - 2 loads of dirt, sliding door pickup, and general cleaning.

2016.05.13 - $30 for truck gas and usage

2016.05.13 - $16 dump fee

2016.05.10 - 7 hours